Oliver Construction Update November 2024
Exterior installations this month include window and curtainwalls, brick veneer, terracotta and metal paneling, drainage trench system, and curbing along Oak Street. Interior installations include continued framing and drywall throughout the new and existing building, ceramic and porcelain tile, ceiling grid and ceiling tile, millwork, and casework placements. Additionally, light fixtures, devices, and cover plates are being installed on the upper floors of the building, and primer coating and finish painting are ongoing.
Click here to see details of Lawrence Oliver for Oliver 2024
Click here to see November 2024 Timelapse video
Click here to see November 2024 exterior drone footage
Click here to see November 2024 interior drone footage
- Details
- Hits: 176
Oliver Construction Update October 2024
Ongoing work includes the installation of windows and curtainwalls, exterior brick veneer, terracotta and metal paneling, interior framing and drywall, ceiling grids for classrooms, and ceramic and porcelain tiling. Light fixtures have started to be delivered and installed on the project site. All electrical systems are now ready for permanent power turn-on. The interior window trim and sills have been advanced. The recharge drainage system of the Southern courtyard has been installed, and classroom casework has started to be placed throughout the building.
Click here to see details of Lawrence Oliver for Oliver 2024
Click here to see October 2024 exterior drone footage
Click here to see October 2024 interior drone footage
- Details
- Hits: 536
Oliver Construction Update September 2024
The installation of exterior brick veneer, salvaged granite, exterior terracotta and metal paneling, and windows and curtainwalls are all ongoing. The team is also continuing to install ceiling grid framing, interior window trim and sills, ceramic wall and floor tile, interior partition drywall and finish, and first coat primer painting. Installation of the new roof system on the existing buildings has been progressing to ensure it is watertight. Installation of light fixtures has also begun and the main feeder cables from the main electrical room are being run throughout the building.
Click here to see details of Lawrence Oliver for September 2024
Click here to see September 2024 exterior drone footage 1
Click here to see September 2024 exterior drone footage 2
- Details
- Hits: 1394
Oliver Construction Update August 2024
Ongoing work includes the exterior brick veneer installation, window and curtainwall installation, terracotta mounting system and insulation, the interior framing and drywall installation, and the installation of MEP systems throughout the building. Painting has begun on the third floor. The repointing of the existing building has been completed and the punch list has now been created. Piping and duct connections have been made to the roof top units and the kitchen hood, freezer, and cooler units have been set in place.
Click here to see details of Lawrence Oliver for August 2024
Click here to see August 2024 exterior drone footage 1
Click here to see August 2024 exterior drone footage 2
- Details
- Hits: 1486
Oliver Construction Update July 2024
The window and curtainwall, brick veneer, and terracotta paneling system installation are all ongoing, along with the repointing of the existing masonry. The drywall installation is close to completion on the 3rd floor and will begin soon on the 4th floor. The rough installation of the fire sprinkler system has continued on the 4th floor and has now begun on the 2nd floor. The roof top units and the emergency generator have been set in place, the stormwater and sewer building tie-ins are now completed.
Click here to see details of Lawrence Oliver for July 2024
Click here to see July 2024 drone footage
- Details
- Hits: 1806
Oliver Construction Update June 2024
The exterior sheathing of the building is now 95% complete. Rough fire sprinkler installation has been completed on the 3rd floor and has started on the 4th floor. Drywall installation has started within the interior of the building, and repointing of the existing building's masonry has begun. Ongoing activities include window and curtain-wall installation, brick veneer installation, terracotta panel system mounting, interior partition and soffit framing, mechanical and electrical utility installation, and site work with building utility tie-ins.
Click here to see details of Lawrence Oliver for June 2024
Click here to see June 2024 drone exterior footage
Click here to see June 2024 drone interior footage
- Details
- Hits: 2623
Oliver Construction Update May 2024
The installation of the exterior framing, sheathing, and air vapor barrier surrounding the building has continued and is getting closer to completion. Roofing installation has also progressed, and mechanical, electrical, and plumbing work continues on all floors throughout the interior of the building. The interior framing within the third and fourth floors has been completed and continues throughout the rest of the building. Beginning work this month includes the installation of brick veneer, terracotta panel support system, and setting of the switchgear system.
Click here to see details of Lawrence Oliver for May 2024
Click here to see May 2024 drone footage
- Details
- Hits: 2686
Oliver Construction Update April 2024
The slab-on-grade placements within the existing building are now complete, along with the majority of the lower-level slab-on-grade placements. The progress of the exterior sheathing and air vapor barrier surrounding the building and windows continues as well. Roofing installation has begun alongside the efforts for the mechanical, electrical, and plumbing work throughout all building floors. Within the existing building, penetrations have been made and lintels have been added for mechanical, electrical, and plumbing conduit. Utility tie-ins progress from Short Street to serve the new building.
Click here to see details of Lawrence Oliver for April 2024
Click here to see April 2024 drone footage
- Details
- Hits: 1908
Oliver Construction Update March 2024
Installation of the exterior sheathing and air vapor barrier has continued on the East side of the new addition and is progressing towards the West. Additional slab-on-grade concrete placements have also occurred and are tracking to be completed in April. The lower level of the new addition has received crushed stone in preparation for pouring the concrete floor base. Installation of overhead mechanical, electrical, and plumbing equipment has also continued throughout all floors of the new addition. The underground utilities and floor of the existing building have been backfilled, and the floor insulation is now being installed on top of it.
Click here to see details of Lawrence Oliver for March 2024
Click here to see March 2024 drone footage
- Details
- Hits: 2093
Oliver Construction Update February 2024
The team continues to install framing and sheathing on the east side of the building addition progressing toward the west side along the exterior. Concrete placements continue throughout the new addition and are on track to be complete early this Spring. Installation of rough overhead mechanical, plumbing and electrical equipment continues throughout the new addition along with fireproofing at steel beams. In the existing building, excavation has been completed for the underground utilities and backfilling of these areas has begun.
Click here to see details of Lawrence Oliver for February 2024
Click here to see February 2024 drone footage
- Details
- Hits: 2411
Henry K. Oliver School Topping Off Ceremony
Cold winter days won't stop the hardworking men and women on site at the new Henry K. Oliver Educational Complex in Lawrence, MA. SMMA joined in the celebration at a special topping off event for the Lawrence community and construction team as the final structural beam was placed for the City’s new K-8 facility.
- Details
- Hits: 1821
Oliver Construction Update January 2024
Steel erection is now complete on site. Final moment and beam connections are now being completed. The project crane has been dismantled and loaded off-site. Slab on deck concrete pours have continued throughout the building. The construction team is working on tarping and heating the building in preparation for the winter. Framing and sheathing work has also begun on the east side of the addition. In the existing building, plumbing lines are being laid out. The project team continues to keep site safety a priority through the winter season and through snowstorms.
Click here to see details of Lawrence Oliver for January 2024
Click here to see January 2024 drone footage
- Details
- Hits: 1924
Oliver Construction Update Topping Off Ceremony
On November 29th, the Henry K Oliver construction team celebrated the Topping Off Ceremony, a milestone celebrating the last piece of steel being erected on the new school. The team was accompanied by the Oliver School Building Committee, students and school leaders, local elected officials, the MSBA, and Mayor Brian A. DePeña. This milestone recognizes the hard work of the construction workers and serves as a symbol of teamwork and achievement for this construction project. Please see the attached PDF for the drone footage of the event.
Click here to see details Lawrence Oliver for Steel Topping Off Ceremony
Click here to see Drone Video Highlight Footage
- Details
- Hits: 1680
Oliver Construction Update December 2023
In the month of November, the Henry K. Oliver Project celebrated a significant milestone in the topping-off ceremony with the last steel beam being hoisted up into the building. The steel erection scope is now almost complete with final bolt connections and welds being finalized. Concrete decks have been poured in the lower floors of the east side of the building addition. The team is now working on tarping off and setting up temporary heating in that section of the addition in preparation for interior scopes of work. Additional work includes drainage connections at the intersection of Short and Oak Street.
Click here to see details of Lawrence Oliver for December 2023
Click here to see December 2023 drone footage
- Details
- Hits: 1557
Oliver Construction Update October 2023
Structural steel and steel decking erection is ongoing on the east side of the new addition. Grade beams are being poured at the West end. In the existing building, window openings are being prepped for window installation. The building’s foundation and waterproofing have now been completed.
Click here to see details of Lawrence Oliver for October 2023
Click here to see October 2023 drone footage
- Details
- Hits: 1301
Oliver Construction Update November 2023
Structural steel and steel decking erection is ongoing on the east side of the new addition. Grade beams are being poured at the West end. In the existing building, window openings are being prepped for window installation. The building’s foundation and waterproofing have now been completed.
Click here to see details of Lawrence Oliver for November 2023
Click here to see November 2023 drone footage
- Details
- Hits: 1398
Oliver Construction Update September 2023
The team has now formed and poured concrete spread footings at the southern part of the new addition. Steel and metal decking have been delivered onsite and are being erected and installed throughout the site with the help of a crane. This will be an ongoing activity throughout the next couple of months. Construction has now moved its way into the existing building with the installation of floor-leveling material and preparations for window installations.
Click here to see details of Lawrence Oliver for September 2023
Click here to see September 2023 drone footage
- Details
- Hits: 1390
May 2022 - July 2023 Drone Footage Time Lapse
Consigli Construction has compiled drone footage from May 2022 to July 2023 to show the progress of the Henry K Oliver School Project site, enjoy the incredible changes that have been made. We are excited for what is still to come!
- Details
- Hits: 1294
Oliver Construction Update August 2023
The team continues to form and place concrete footings between the existing and new buildings. Foundation walls are being waterproofed, followed by install of foundation drainage and topped off with crushed stone. Underground plumbing installation is ongoing within the new concrete mat slab. The Learning Stairs are being formed and poured as the team works their way up to the existing building.
Click here to see details of Lawrence Oliver for August 2023
Click here to see July 2023 drone footage
- Details
- Hits: 1180
Oliver Construction Update June 2023
Placement of concrete foundation walls continues along the building perimeter. Existing utilities have been run across Haverhill Street and connected to the project site. Elevator shaft installation is nearly complete.
- Details
- Hits: 1302
Oliver Construction Update May 2023
Concrete mat slab placement is now complete. Rebar installation for the foundation walls and spread footings has started along with the CMU elevator shaft installation. Utility work has commenced onsite. The next step for the team is to prepare foundation walls for concrete pour.
Click here to see details of Lawrence Oliver for May 2023
Click here to see aerial footage of construction site for May 2023
- Details
- Hits: 1411