The new Francis M. Leahy School K-8 is being constructed on the location of the former Leahy School and joins the Oliver project as Lawrence’s first new school building in more than two decades. The 1,000-student school complex will combine the Leahy Elementary, Lawlor and Leonard Middle School under one roof. The City of Lawrence has partnered with the Massachusetts School Building Authority, from which partial grant reimbursement will be received. Construction of the new School is ongoing with anticipated occupancy for the start of the academic year in the fall of 2025.
Average daytime temperature of 78 degrees, with three days in the low 90’s. There was less than 2” of rain, having minimal impact to progress. The storm water detention area was excavated, and structures set. Work is expected to continue through most of September. To find a more detail progress update check out the report listed below.
Leahy August Update Progress Report