The installation of the exterior framing, sheathing, and air vapor barrier surrounding the building has continued and is getting closer to completion. Roofing installation has also progressed, and mechanical, electrical, and plumbing work continues on all floors throughout the interior of the building. The interior framing within the third and fourth floors has been completed and continues throughout the rest of the building. Beginning work this month includes the installation of brick veneer, terracotta panel support system, and setting of the switchgear system.